The bare yurt frame lit up from inside at night, lattice walls and roof rafters glowing against a dark blue sky

Our story · 物語

Built by hand at the foot of Moiwa

People ask us all the time how this place was built. The short answer: one builder, one digger for the posts, and a few extra hands to get the roof on. Here's the long answer, from an empty ski run in September to opening night on Christmas Eve.

18 Sep – 24 Dec 2024 · 30ft across · built by hand

  1. 18 – 20 Sep 2024

    An empty ski run

    It started with a patch of grass at the bottom of Moiwa and a few marker stakes. Two days later the excavator was in, digging the holes for the foundations.

    The empty grassy ski run at the base of Moiwa with a survey stake in the ground Wooden stakes marking out the footprint on the grass A small orange excavator digging foundation holes
  2. 26 – 29 Sep 2024

    Standing on logs

    Instead of concrete piers, the yurt stands on whole logs. They came from the Aman hotel development going up just a few hundred metres away. They arrived on the 26th, and the next day each one was lifted by the digger and stood upright in its hole. By the 29th they were braced and working into the night.

    A row of cut logs lying on the grass, ends marked with red paint A log hanging from the excavator bucket being guided into its hole The log posts standing upright in a circle The braced log posts lit by a work light at night
  3. 1 – 15 Oct 2024

    The platform

    Bearers went across the logs, then joists, then the round edge of the deck took shape. Insulation went in between the joists and the plywood deck went down on top. The last sheets were laid by floodlight in the early hours of 15 October. At its highest point, the deck sits about 3 metres off the ground.

    Timber bearers laid across the tops of the log posts The round timber frame of the platform on its posts Insulation boards laid between the floor joists The finished round plywood deck lit by work lights at night
  4. 16 Oct 2024

    Up in a day

    At 8am on 16 October the deck was bare. By lunchtime the lattice walls and door were in. By late afternoon the crown ring was up on the scaffold and the rafters were going in around it. At 6:30 that night we switched the lights on inside the frame. A few extra hands came up to help get the roof on. The finished circle is 30 feet (about 9 metres) across.

    The bare round deck with scaffolding in the middle, morning
    8:23am
    Lattice walls and the door frame going up around the deck
    10:23am
    A builder standing on the scaffold inside the crown ring as the first rafters go in
    4:17pm
    Looking up through all the rafters to the open crown ring at dusk
    5:50pm
    The lattice walls of the frame lit up from inside against the night
    6:38pmLights on in the frame for the first time.
  5. Oct – 18 Nov 2024

    Under canvas

    Tarps kept the weather out while the roof was insulated and the canvas was fitted over the top. By mid-November the red walls were on. Five days later, the first snow settled on the roof.

    The frame wrapped in blue tarps on its log posts Looking down on the roof from above, insulation laid around the open crown The yurt with its red canvas walls and roof cover on, autumn trees behind The finished yurt under the first snow, logs stacked out front
  6. 22 Nov – Dec 2024

    Fitting out

    Then came the mad scramble: getting the inside built, licensed and open before the season. Our staff pitched in on the fit-out. The floor went down, the bar and kitchen were framed up against the lattice, and the fridges and equipment came in through the door.

    Inside the yurt: the door frame and first floor panels going down The bar framed up in plywood inside the yurt Fridges and equipment arriving inside, timber floor laid
  7. 5 – 19 Dec 2024

    The bar top

    The bar top was milled on site from a single log, on a sawmill set up outside in falling snow. It went onto the bar a few days later, and was sanded back late at night while the snow kept piling up outside.

    Milling a log into a slab on a portable sawmill in falling snow The rough slab bar top in place on the bar Sanding the slab bar top at night, dust in the work lights The finished bar with the timber floor in front
  8. 22 – 24 Dec 2024

    Lights on

    Strip lights went along every rafter, the paper lanterns went up under the crown, and the coffee machine fired up for the first time. On 24 December 2024, Christmas Eve, the doors opened.

    Lights running along every rafter, a ladder still up in the middle of the room Pouring the first beer from the tap behind the bar
    The finished room: lit rafters, long timber tables, lounge chairs and the bar
    The Chairman's LoungeOpen since Christmas Eve 2024, at the base of Moiwa.
The yurt in summer, green grass and forest around it

Since then

Still standing

The yurt stays up all year. In summer it sits in the long grass at the bottom of the hill, waiting for the snow to come back.

See what's on this winter